The Shepard Point Oil Access Project is an ongoing project that will help accelerate response times to oil spills. Hilfiker was chosen to supply the materials to build an access road to the monitoring station, with our contributions including several true bridge abutments with full load capacity, 7 trinity walls, and a boat ramp.
The walls and abutments varied in size with a max height of 38 feet and a combined 23,477 square feet of materials.
This project was constructed by Turnagain Construction, designed by Shannon & Wilson and GHD, and is owned by the Native Village of Eyak.
Drone video of the access road and the various abutments built to support them.
Wall Type:
Trinity
Wire Type:
Galvanized
Owner Type:
Government
Wall Height:
Over 30'
Wall Size:
Over 5000 SF
60, 145